On January 7, 2024, the East Tower of MU Yiwu Building successfully reached its topping-out ceremony, marking a critical milestone and significant achievement in the construction project.
Situated in the financial business district, the project covers a total construction area of nearly 120,000 square meters, integrating various functions such as offices, exhibition halls, and staff apartments. It can accommodate the office needs of 5,000 people, comprising the East and West Towers, with heights of 19 and 23 floors, respectively. The underground structure spans three floors with an area of 30,000 square meters. The comprehensive topping-out is expected to be achieved in March of this year.
Looking back on the construction process of two years and four months, the project started clearing the site in May 2022 and officially commenced construction on August 3, 2022. While ensuring safe construction and project quality, every effort has been made to guarantee construction progress, ensuring efficient and high-quality completion for commissioning.
MU Yiwu Building is not only a crucial step in the group’s deepening localization of business in Yiwu and accelerating digital transformation but is also believed to contribute significantly to the construction of the “Sixth Generation Market” in Yiwu.